17 Stormwater Conditions Mandated for Main Street Extension Contractor Bays Following Drainage Review

Key Points

  • Contractor bay project at 103 Main Street Extension received approval with 17 conditions focusing on 50-year and 100-year storm drainage capacity.
  • Planning Board accepted a $256,000 financial security bond from Eastward MBT LLC to guarantee road and utility completion for the Orleans Road subdivision.
  • Historical evidence of Anesus Road predating 1949 subdivision laws allowed for the division of an 8-acre parcel at 99 Queen Anne Road.
  • Local Comprehensive Plan draft entered its final 60-day public comment phase with a deadline of September 30 for board and resident feedback.

Construction of a 4,800-square-foot pre-fabricated metal building at 103 Main Street Extension moved forward Tuesday night, but only after the Planning Board imposed rigorous new requirements for the site’s drainage systems. Mark Dib of Cape and Islands Engineering presented revised plans to the board, noting that the team had added some capacity to both systems in the front and in the back in order to address concerns about different size storms, emergency overflow, and additional storage. Planning Director Christine Flynn confirmed that the town’s consulting engineer from VHB felt the applicant had addressed the primary technical concerns regarding runoff.

During the hearing, Chair Duncan Berry scrutinized the specific elevation of catch basins to prevent surcharging during a 25-year storm event. Dib replied that the solution was simple: We actually added some storage to that system. While the board granted a waiver regarding the standard requirement for one tree per five parking spaces to preserve existing greenery, the final approval was heavily conditioned. Motion Made by A. Peterson to adopt the findings of fact Passed (5-0-2) with M. Maslowski and H. Munns abstaining. Motion Made by A. Peterson to approve the site plan with 17 conditions, including requirements for the drainage system to handle 100-year storm events, Passed (5-0-2). Member Emily Brutti supported the motion, which requires full building design plans to be submitted prior to any building permits being issued.

The board also authorized a significant financial security agreement to ensure the completion of infrastructure at 1594-98 Orleans Road. Susan Leoo, representing Eastward MBT LLC, requested a full release of covenants for the remaining six lots in the subdivision. Flynn recommended that the board accept a financial surety of $256,000 to cover the remaining cost of the road installation as well as municipal services. Motion Made by M. Maslowski to accept the $256,000 security and release the remaining lots Passed (7-0-0). Motion Made by M. Maslowski to confirm the financial security agreement Passed (7-0-0).

In other business, the board untangled the complex history of Anesus Road to facilitate a land division at 99 Queen Anne Road. Attorney Peter Freeman, representing MidCape Church Homes, Inc., explained that the plan divides an 8-acre parcel into two lots, with one portion to be retained by Richard Welsh and the other conveyed to Queen Anne Acres LLC. The project’s status hinged on whether the unpaved road qualified as an existing way prior to 1949 subdivision laws. Flynn noted that Town Counsel had reviewed the documentation and determined the road predated the laws, though she cautioned that this should not be seen as a precedent setting of not requiring appropriate deed access when we evaluate other unpaved roads in the future.

John McKelway of Cape and Islands Engineering described the site as having frontage analysis of 160 feet and sitting within both industrial and residential zones. When Berry asked if board members had concerns regarding the width or grading of the road following a site visit, A. Peterson replied, No. M. Maslowski added that she had also reviewed the site independently. Motion Made by M. Maslowski to endorse the approval not required plan based on findings that the way predates 1949 and has sufficient gradient Passed (7-0-0).

The meeting concluded with an update on the Local Comprehensive Plan (LCP), which Flynn noted has entered a 60-day public comment period ending September 30. M. Maslowski asked, Should we put that on as a discussion topic for our September 9th meeting? to ensure the board provides formal feedback before the deadline. The board, including Ann Clark Tucker and Ann Newman, also noted that the next session will include an outline of concerns for the 242-unit Pine Oaks Village 4 project, focusing on parking, traffic, and stormwater impacts to be shared with the Zoning Board of Appeals.